"The Fish Pond Project" –
Phase 1A: Revealing the Hidden Feature

Photo: Fountain/pond completely obscured by shrubberySaturday, September 12, 2009 – The week had been quite wet. It was questionable whether or not Society volunteers would be able to begin removing the shrubbery and dig out the dirt that totally obscured the fountain/pond (top right).

Photo: With the shrubbery already removed, digging was able to begin immediately on the fountain/fishpondThe team members were pleasantly suprised to find that, not only was the ground dry enough to work with, but also Leo Massiate, Thomas Jeffrerson's Groundskeeper had taken the time during the week prior to the Society's planned workday to remove the shrubbery that filled both the middle and outer hexagons of the fountain/pond. Only the soil remained between the anxious group and the beautifully tiled architectural feature the Society is seeking to restore (bottom right). This saved a considerable amount of time, and allowed the team to immediatley begin the "digout."

Phase 1A Milestones

Milestone #1 (8:00 – 8:40 a.m.): The workforce arrives

The following workers were present:

  • Tom Murrah - Society Board President
  • Patsy Skeels - Society Board Treasurer
  • Susan Frost-Toomey - Society Advisory Board member
  • Don Moore - Society Board member (web manager)
  • Charles Bartlett - volunteer
  • Albert Del Rio - volunteer
  • Joe Wofford - volunteer
  • Barbara Wofford - Society Board Vice-President
  • Christine Mendiola - Society Board member and Jefferson Principal
  • Juan Saucedo - volunteer and Head of Jefferson Maintenance Staff
  • John Huron - Society Board Recording Secretary

Let the record show that, except for our youngest member who arrived after family business was taken care of at about 11:30, the bulk of the work was carried out by a team of dedicated individuals with ages ranging from the youngest at 58 to the oldest at 82. Now what kind of individuals does Jefferson turn out into the world? (The answer is not "older ones")

Milestone #2: Time put into project

Between this group and Mr. Massiate, Jefferson Groundskeeper, a total of 54.25 man-hours of work were put into the project by the Board and its supporters. This kind of dedication is what makes a service-oriented nonprofit succesful. Thanks to all who took part.

Milestone #3 (8:45 a.m.): The "middle hexagon" is revealed

Photo: The middle hexagon of the student council patio fountain/fishpond is revealed The photo to the right shows Patsy Skeels and Charles Bartlett sweeping and shoveling the last bit of soil out of the middle of the two hexagons that make up the fountain/pond. Being the most shallow part of the architectrual feature and filled only with a good topsoil/mukch mix, the digging was somewhat easier, and it was able to be revealed within the first hour of the project.


A major part of the inner hexagon is the plaque on its outer wall marking the fountain/pond as a gift from the first Senior/graduating Class at Jefferson in 1932, the year the school opened. Note the damage to the tiles on this outer wall of the inner hexagon (left).


Milestone #4: The deep hexgonal pool

Photo: Deep into the out hexagon digThe first 3-1/2 feet of the outer nexagon were also filled with the topsoil/mulch mix, but beyond that, the team began to encounter the thick black clay-like soil that did not give easily to the shovel but hung onto the shovel's nose until it was scraped off by hand. This really slowed down progress. But with the shining blue tiles that lined the tope 2-3 feet of the inner hexagon showing, the team was inspired to carry on until well after the high-noon Sun began beating down on them.


Milestone #5: Closing the project for the day

Phtot: Construction barrier around fountain/pondAt 1:30, the Sun letting everyone know that it was time to be inside, the team completed a visual barrier with the hopes that no one would cross it to try to jump into the newly dug trenches. Board member, John Huron, made a run to a building supply store to secure posts and construction mesh that was erected around the outer hexagon of the foutain/pond.

   
 
Thomas Jefferson High School Historical Preservation Society | Non-profit IRS designation 501(c)3 organization
Mr. Tom Murrah; PO Box 5567; San Antonio, TX 78201
©Copyright 2008 Thomas Jefferson High School Historical Preservation Society. All Rights Reserved.